Endeavour Silver Puts Pitarrilla Build at US$585 Million
Endeavour Silver stock fell Nov. 20 in Toronto. We compare Pitarrilla's build estimate with reported cash and test gross sales at lower silver prices.
by Corinne Ashdown3 min read

Endeavour Silver (TSX: EDR; NYSE: EXK) estimates it would cost US$585 million to build Pitarrilla, an underground silver mine in Durango, Mexico, according to its Nov. 19, 2026 feasibility results. Its Nov. 20 presentation describes the project as “advancing toward a construction decision.”
At 1:13 p.m. ET on Nov. 20, TMX Money's Toronto quote showed Endeavour Silver stock trading about 6% lower. Kitco reported a decline in spot silver to US$41.65 an ounce in its morning report updated at 9:02 a.m. ET on Nov. 20. Neither snapshot establishes what drove the Toronto share move or whether the study contributed.
The proposed mill would be designed to process 4,000 tonnes a day. The study projects average production of 7.5 million silver-equivalent ounces a year over an 18-year mine life. Silver-equivalent ounces express the lead and zinc output in terms of the value of silver, so the headline output includes all three metals. The study puts after-tax net present value at US$736 million using a 5% discount rate, which gives less weight to cash further out. It estimates an after-tax internal rate of return of 16.37%.
Would Pitarrilla still pay at Friday's silver price? The study assumes US$50 an ounce and puts break-even below US$30 an ounce. Friday's price clears that threshold if the other inputs hold, while the US$736 million valuation belongs to the base case. Holding silver at Friday's US$41.65 over the mine's life in place of the study's US$50 assumption would cut average annual gross silver sales by about US$41 million, by our arithmetic. That uses the study's 88.7 million payable silver ounces and holds production and other prices constant. It gives us neither a revised net present value nor a cash-flow estimate.
How Much Cash the Existing Mines Would Need to Free Up
Endeavour expects to fund most of construction with “cash on hand and cash flow from its operating mines.” Its Nov. 9 quarterly results put cash at US$287.9 million on Sept. 30. By our arithmetic, even putting that whole balance toward Pitarrilla would leave US$297.1 million to fund, before setting aside any cash for the rest of the business.
If Endeavour covered that illustrative remainder entirely with cash retained from operations over two years, it would need about US$37 million a quarter after the mines' own spending and other corporate obligations. The two years are our test window; the company hasn't given that schedule.
For the September quarter, Endeavour reported US$48.4 million in “operating cash flow before working capital changes,” a company-wide non-IFRS measure. That figure comes before capital spending and doesn't tell us how much Terronera or Kolpa could contribute. Retaining more cash from operations could limit the need for new debt or shares, while weaker silver prices could make that cash harder to free up.
In Vizsla Silver Moves Panuco's First Silver Target to 2028, we separated the value in a mine plan from the timing of its cash. For Endeavour holders, the timing to watch comes before production: bills fall due during construction, while Endeavour expects its other mines to help pay them.
Endeavour says it has key permits for underground mining and development, as well as for explosives, water use and discharge, and changes in land use. The company still needs other approvals and amendments, among them the Tailings Storage Facility Permit. Tailings are the waste left after ore is processed.
Endeavour says it will file the technical report on SEDAR+ within 45 days of Nov. 19. By early January 2027 we'll be looking for the spending schedule and the lower-price cases; the release gives no date for a construction decision.
Seek the truth and be prepared,
Equedia News
Sources
- Endeavour Silver, Pitarrilla feasibility study results as released via GlobeNewswire and carried by TMX
- Endeavour Silver, Pitarrilla feasibility study presentation
- TMX Money, Endeavour Silver's Toronto quote
- Kitco, Nov. 20 morning report on the silver selloff
- Endeavour Silver, Third-quarter financial results and updated guidance
- Equedia, Vizsla Silver Moves Panuco's First Silver Target to 2028