The Federal Energy Regulatory Commission voted on November 19, 2026, to authorize three more liquefaction trains at Sabine Pass, the existing LNG terminal in Louisiana's Cameron Parish, according to the commission's release and meeting summary. The vote authorizes Sabine Pass Liquefaction, LLC and Sabine Pass Liquefaction Stage V, LLC to build and operate the trains.
A liquefaction train chills natural gas into a liquid for shipment. The vote lets Cheniere Creole Trail Pipeline L.P. expand the Creole Trail Pipeline Project. It also lets Sabine Crossing Pipeline build and operate a new interstate gas line serving the terminal.
For holders of Cheniere stock and CQP units, the vote clears the facilities while the partnership still has to decide whether to commit the capital.
Cheniere Energy Partners (NYSE: CQP) put the full Stage V expansion at up to about 20 million tonnes of liquefied natural gas (LNG) per year at peak in its May 28 project update. Train 7 anchors the first phase, whose total expected capacity exceeds 6 million tonnes per year. Both estimates include output gains from removing production bottlenecks.
How much capital would the expansion take? In its October 29 results, the partnership said it and its subsidiaries obtained term loan commitments in September. The loan was being sized at about half the first phase's estimated cost, for expenses “not expected to be funded with available cash.” Closing and funding still depend on a positive first-phase investment decision, among other conditions. The disclosures we could verify give us the intended loan share without a dollar budget for the first phase or the full build.
The Stage V subsidiary gave its contractor limited authorization to begin early engineering and procurement, and the partnership says long-term sales agreements support the first phase. In October the partnership still listed its application to the US Department of Energy to export to countries without a US free trade agreement as pending. FERC's facility vote gives no update on that separate application, whose November 19 status we could not verify from these disclosures.
The QatarEnergy contract gives us a delivery window. Cheniere Partners says deliveries from Sabine Pass would begin in the early 2030s and could reach 2 million tonnes a year. Of that maximum, 1 million tonnes a year depends on a positive first-phase investment decision, among other conditions. The contract does not establish when Train 7 or the later trains would ship their first cargoes.
Sabine Pass Gives CQP the More Direct Exposure
For Cheniere Energy (NYSE: LNG) shareholders, Sabine Pass is a source of potential growth alongside Corpus Christi, where the company reported in October that it had substantially completed its Stage 3 expansion. For CQP unitholders, the upside is more output at the partnership's own terminal. The partnership takes anticipated cash-funded capital spending into account when it sets the variable part of its distribution, so construction spending could leave less room for that payout.
The pipeline projects, if built, would help move more US gas to Sabine Pass once the new trains run. For producers, that's a potential longer-term outlet, separate from the winter inventory cushion we covered in US Gas Stocks Rise 77 Bcf as Surplus Widens.
We'll watch separately for a DOE decision on exports and for any published construction budget and schedule. For the first-phase investment decision, the date to test is early 2027, the target the partnership gave in May.
Seek the truth and be prepared,
Equedia News
Sources
- Federal Energy Regulatory Commission, FERC Approves Major Gas Infrastructure Facilities to Get American Energy Moving
- Federal Energy Regulatory Commission, Summaries of the November 2026 Commission Meeting
- Cheniere Energy Partners, Cheniere Partners Signs EPC Contract with Bechtel for the First Phase of the Sabine Pass Expansion Project and Issues Limited Notice to Proceed
- Cheniere Energy Partners, Cheniere Partners Reports Third Quarter 2026 Results and Tightens Full Year 2026 Distribution Guidance
- Cheniere Energy, Cheniere Reports Third Quarter 2026 Results, Raises Full Year 2026 Financial Guidance, and Increases Quarterly Dividend by Over 12%
- Equedia News, US Gas Stocks Rise 77 Bcf as Surplus Widens
Disclaimer: This letter is for informational and educational purposes only and does not constitute investment advice. Past predictions and performance are not indicative of future results. Please see our full terms of use and disclaimer at equedia.com.