Codelco, Chile's state copper producer, reported a net loss of US$377 million for January to September 2026 after a US$4.82 billion non-cash write-down, according to its Nov. 27 results release. Its nine-month report puts the pre-tax loss at US$1.4 billion, against a pre-tax profit of US$607 million a year earlier.
The loss came in a year of much higher copper prices. Codelco realized an average 670.0 cents a pound, up 45.2 per cent, and its adjusted EBITDA rose 80.2 per cent to US$7.5 billion. That measure, as the report defines it, adds impairment charges back, so the write-down left it untouched.
Codelco impairment charges by division, nine months to Sept. 30, 2026
US$ million
Source: Codelco results release, Nov. 27, 2026
| Label | Value |
|---|---|
| Chuquicamata | 3024 |
| Salvador | 1598 |
| Gabriela Mistral | 198 |
Chuquicamata carries US$3.024 billion of the charge, which the release explains mainly by updated long-term operating and economic projections. Salvador's US$1.598 billion reflects higher costs and changed market assumptions, and the report adds the extended suspension of its smelter and refinery. Gabriela Mistral's US$198 million is tied mainly to weaker operating performance. The release says the charge reflects "un retorno no esperado de los proyectos estructurales", a return on its structural projects that Codelco had not expected.
Codelco's own production fell 9.0 per cent to 853,000 tonnes, the report shows. Its own copper sales fell faster, by 17.6 per cent to 920,700 tonnes, and neither document gives a reason for that gap. The release puts the lower output down mainly to El Teniente, where some sectors remain restricted after the 2025 accident, to Chuquicamata's haulage-belt maintenance, and to a revised geological model and depleted grades at Ministro Hales.
Codelco copper output by mine, nine months to Sept. 30, 2026
Change on a year earlier, per cent; partner mines at Codelco's share
Source: Codelco, Nine-Month 2026 Operational and Financial Report, Nov. 27, 2026
| Label | Value |
|---|---|
| Ministro Hales | -32.4 |
| El Teniente | -17.1 |
| Chuquicamata | -12.4 |
| El Abra (49%) | -11.5 |
| Gabriela Mistral | -3.6 |
| Salvador | 2.5 |
| Andina | 3.6 |
| Radomiro Tomic | 3.7 |
| Anglo American Sur (20%) | 7.1 |
| Quebrada Blanca (10%) | 17.8 |
The direct C1 cash cost rose 10.1 per cent to 237.9 cents a pound, a rise the release attributes mainly to lower output and dearer acid, energy and fuel, partly offset by better by-product prices, chiefly molybdenum, and treatment and refining charges. C3, the net cost to cathode, rose 8.6 per cent to 402.5 cents.
Codelco, wholly owned by the Chilean state, has no listed shares, so its results reach you through its partners, its bonds and the metal.
At El Abra, which Freeport-McMoRan (NYSE: FCX) lists among the mines it operates in South America, Codelco's 49 per cent share came to 30.7 thousand tonnes, down 11.5 per cent. Because the report counts 49 per cent of the mine's total, by our arithmetic El Abra as a whole fell by the same 11.5 per cent.
Quebrada Blanca went the other way. Teck Resources (NYSE: TECK) holds an indirect 60 per cent of it and Codelco a 10 per cent non-funding interest, according to Teck. The tonnes Codelco books from that stake rose 17.8 per cent to 15.9 thousand. At Anglo American Sur, where it counts 20 per cent, its tonnes rose 7.1 per cent to 33.2 thousand.
Codelco's equity-method profit from associates and joint ventures rose to US$376 million from US$85 million, and the report says the rise mainly reflects "the inclusion of the lithium business operated with SQM" (NYSE: SQM). It gives no separate figure for that business.
For Codelco's bondholders, net debt rose US$638 million in a year to US$24.4 billion on Sept. 30. Its ratio to trailing adjusted EBITDA fell to 2.4 times from 4.3 times. The report adds that on Nov. 2 Fitch affirmed its BBB+ long-term foreign rating, with a stable outlook.
No Date Yet for Codelco's Recovery Plan
Neither document restates the lowered 2026 production forecast we covered in Codelco Lowers Its Copper Output Forecast, so these nine months alone cannot show whether Codelco will reach it.
"Codelco enfrenta desafíos operacionales y financieros importantes. Tras un diagnóstico de nuestras operaciones y de la situación financiera de la compañía, implementaremos el Plan de Recuperación que estamos elaborando."
Chief executive Jorge Gómez said in the release that Codelco faces major challenges and is drafting a recovery plan, with stable operations and safety first and lower costs in the near term. The release gives the plan no date.
The report expects the Andes Norte suspension at El Teniente to last into the medium term. Its overstated-output estimates for 2024 and 2025 stay preliminary while the investigations continue, among them the forensic audit the board commissioned from EY.
James Galatoire becomes vice-president of projects on Dec. 1, and Salvador's Rajo Inca project is due for full completion by the end of 2026, the report says. Carlos Olavarría Brown becomes vice-president of marketing on Jan. 1, 2027.
Seek the truth and be prepared,
Equedia News
Sources
- Codelco, Codelco aumenta sus aportes al fisco en 57% y realiza ajuste contable para reflejar el valor real de sus activos, Nov. 27, 2026
- Codelco, Nine-Month 2026 Operational and Financial Report, Nov. 27, 2026
- Freeport-McMoRan, South America operations
- Teck Resources, Quebrada Blanca
- Equedia News, Codelco Lowers Its Copper Output Forecast
Disclaimer: This letter is for informational and educational purposes only and does not constitute investment advice. Past predictions and performance are not indicative of future results. Please see our full terms of use and disclaimer at equedia.com.